Sadhu Vaswani Bridge: Main Section to Be Dismantled in 12 Segments Using Giant Cranes

The bridge was a key connector between Koregaon Park and Camp area, but structural assessments deemed it unsafe for further vehicular use.
Sadhu Vaswani Bridge
Sadhu Vaswani Bridge The Bridge Chronicle
Published on

Pune Municipal Corporation (PMC) has taken a major step toward reconstructing the Sadhu Vaswani Flyover in Koregaon Park by commencing the removal of its main section over the railway tracks.

The bridge, which has served Pune for over five decades, will be dismantled in 12 separate segments over the course of 12 days. This work will be carried out as per the railway administration’s scheduled block timings.

Sadhu Vaswani Bridge
Sadhu Vaswani Bridge: Slum Relocation and Railway Approvals Stall Reconstruction Work

The Sadhu Vaswani Bridge was a key connector between Koregaon Park and the Camp area, but structural assessments by PMC deemed it unsafe for continued vehicular use. While the foundation stone for a new bridge was laid, demolition faced delays due to technical complexities, particularly in removing the portion over the railway lines. Following extensive coordination with the railway administration, the necessary work blocks have now been approved, allowing for the final phase of dismantling.

Sadhu Vaswani Bridge
Sadhu Vaswani Bridge Demolition 20% Complete, Full Project to Finish by 2026

Use of Advanced Crane Technology to Expedite Demolition
To efficiently remove the bridge’s main section, two heavy-duty cranes have been brought in from Gujarat and Hyderabad. Transporting and assembling these cranes required 22 containers and took nearly a month. The demolition plan involves cutting the bridge into 12 concrete segments, with one segment removed daily. Under normal circumstances, this process would have taken 50 days, but with the use of these cranes, PMC aims to complete the task within just 12 days. The entire operation will be conducted under the close supervision of railway authorities.

“The removal of the main section of the Sadhu Vaswani Bridge will begin shortly. This marks the first instance of large-scale crane usage for bridge demolition within Pune Municipal Corporation limits, ensuring faster execution.”
– Yuvraj Deshmukh, Chief Engineer, Special Projects Division, PMC

Help Us Create the Content You Love

Take Survey Now!

Enjoyed reading The Bridge Chronicle?
Your support motivates us to do better. Follow us on Facebook, Instagram, Twitter and Whatsapp to stay updated with the latest stories.
You can also read on the go with our Android and iOS mobile app.

Related Stories

No stories found.
logo
The Bridge Chronicle
www.thebridgechronicle.com