Pune Equal Water Supply Scheme Reaches 88% Completion, Metered Supply Trials to Begin Soon

60 of 144 water zones ready, 63 out of 83 tanks complete; PMC plans dummy bills and meter readings within a month
Pune Equal Water Supply Scheme Reaches 88% Completion, Metered Supply Trials to Begin Soon
Pune Equal Water Supply Scheme Reaches 88% Completion, Metered Supply Trials to Begin SoonThe Bridge Chronicle
Published on

Pune, 2nd September 2026: Pune Municipal Corporation’s (PMC) Equal Water Supply Scheme is nearing completion, with 88% of the work now finished. The civic body plans to begin metered water supply in phases, starting with zones where the required infrastructure has been completed.

Join our WhatsApp Channel to Stay Updated!

PMC Additional Commissioner Pavniet Kaur said maintenance and repair work for completed infrastructure in 60 zones will be handed over to Larsen & Toubro (L&T). Meter readings will initially be carried out on a trial basis, followed by the preparation of dummy water bills.

“The plan is to start meter reading in selected zones within the next month and issue dummy bills to residents. This will help the PMC test the system before metered water supply is implemented across the city,” Kaur said.

Pune Equal Water Supply Scheme Reaches 88% Completion, Metered Supply Trials to Begin Soon
Pune Civic Body to Curb Water Tanker Mafia with New SOP, Introduces GPS Tracking and Online Booking

The project was introduced to improve water distribution, reduce leakages and ensure more equitable supply across Pune. Although the scheme was approved eight years ago, several components are still being completed.

So far, the PMC has:

  • Completed 63 of the 83 planned water tanks

  • Laid around 1,000 km of new pipelines

  • Installed most of the planned 2.75 lakh water meters

  • Kept around 40,000 meters pending for installation

Pune Equal Water Supply Scheme Reaches 88% Completion, Metered Supply Trials to Begin Soon
Pune's Water Demand May Double by 2047; Maharashtra Prepares Long-Term Water Security Master Plan

Kaur said another 16 tanks are expected to become operational by September 10. Land availability issues are delaying pipeline work in some locations, while opposition to meter installation has also slowed progress in certain areas.

The PMC has divided the city into 144 water supply zones under the scheme. Infrastructure work has been completed in 60 zones, including water tanks, pipelines and meters.

Once these systems are fully operational, L&T will take up their maintenance and repair. The PMC intends to complete the remaining work quickly so that metered water supply can gradually be extended to residents across the city.

Pune Equal Water Supply Scheme Reaches 88% Completion, Metered Supply Trials to Begin Soon
Pune: 200 MLD Water Treatment Plant to Get 2.5 Hectares of CWPRS Land in Khadakwasla

The scheme is also aimed at improving water management as Pune continues to expand and its water demand rises. The civic administration plans to use meter readings to measure consumption more accurately and identify areas of water loss.

Chief Minister Devendra Fadnavis has repeatedly directed the PMC to implement metered water supply and improve water management.

Officials said the progress of the Equal Water Supply Scheme is also being reviewed through meetings involving the Chief Minister’s Office.

The PMC is now focusing on completing the remaining infrastructure and beginning trial operations in ready zones before moving towards citywide metered water supply.

Join our WhatsApp Channel to Stay Updated!

Help Us Create the Content You Love

Take Survey Now!

Enjoyed reading The Bridge Chronicle?
Your support motivates us to do better. Follow us on Facebook, Instagram, Twitter and Whatsapp to stay updated with the latest stories.
You can also read on the go with our Android and iOS mobile app.

logo
The Bridge Chronicle
www.thebridgechronicle.com