Pune: Katraj–Kondhwa Road May Miss March 2027 Deadline as Land Acquisition Remains Pending

Measurement, fresh award and administrative procedures for 10 properties may take another three to four months; delay could put the PMC’s March 2027 deadline for completing the 50-metre road under pressure.
Pune: Katraj–Kondhwa Road May Miss March 2027 Deadline as Land Acquisition Remains Pending
Pune: Katraj–Kondhwa Road May Miss March 2027 Deadline as Land Acquisition Remains PendingThe Bridge Chronicle
Published on

Pune, 22nd September 2026: The Pune Municipal Corporation’s (PMC) plan to complete the 50-metre Katraj–Kondhwa road by March 2027 could face delays as land acquisition for 10 properties required for the project is still pending. The land acquisition proposal has been sent to the government, but the measurement of the properties has not yet been completed.

Join our WhatsApp Channel to Stay Updated!

Officials said the measurement, preparation of a new award and other administrative procedures could take another three to four months. The civic body can take possession of the properties only after these procedures are completed.

Pune: Katraj–Kondhwa Road May Miss March 2027 Deadline as Land Acquisition Remains Pending
Pune: Katraj-Kondhwa Road Widening Faces Fresh Land Acquisition Hurdle

Around 60% of the service road work has been completed. The PMC road department has planned to finish most of the remaining work within a month, except at locations where properties at Sundarban and Maulinagar Chowk are creating obstacles.

Completion of the service road is expected to reduce traffic pressure on the main Katraj–Kondhwa road and improve movement for local residents. However, the remaining property-related issues are also affecting the progress of the main road work.

Properties in the Sundarban area and four structures at Maulinagar Chowk are yet to be cleared. These properties are required for the proposed grade separator and bridge works.

The administration has not yet provided a clear timeline for completing the acquisition, taking possession of the properties and handing over the sites for construction.

Pune: Katraj–Kondhwa Road May Miss March 2027 Deadline as Land Acquisition Remains Pending
Pune Civic Body Approves ₹3,722 Crore Land Acquisition for HCMT Road, Inner Ring Road

Chief Land Acquisition Officer Shweta Darunkar said the proposal has been received from the District Collector’s Office and correspondence is currently underway.

"The District Collector’s Office has sent the proposal and correspondence is in progress. We have also informed them that the matter is urgent. Once the notices are issued and the measurement is completed, we will take possession of the properties immediately," Darunkar said.

Local resident and advocate Prabhakar Todkar said the pending land acquisition raises questions over the PMC’s March 2027 completion target.

"The administration has assured that the road will be completed by March 2027. However, if the land acquisition process is still pending, it is unclear how the deadline will be met. The administration should give priority to the acquisition process and announce a clear timeline," Todkar said.

Pune: Katraj–Kondhwa Road May Miss March 2027 Deadline as Land Acquisition Remains Pending
Pune District Administration Speeds Up Land Acquisition for HCMT Road and Inner Ring Road Projects

With land acquisition still pending at key locations, the pace of the Katraj–Kondhwa road project will depend on the completion of measurement, acquisition and site clearance. The progress of the proposed grade separator and bridge will also remain linked to these processes.

Join our WhatsApp Channel to Stay Updated!

Help Us Create the Content You Love

Take Survey Now!

Enjoyed reading The Bridge Chronicle?
Your support motivates us to do better. Follow us on Facebook, Instagram, Twitter and Whatsapp to stay updated with the latest stories.
You can also read on the go with our Android and iOS mobile app.

logo
The Bridge Chronicle
www.thebridgechronicle.com