Pune Municipal Corporation Prioritizes 33 Missing Link Roads to Reduce Traffic Congestion

Pune civic body plans ₹1,200 crore road infrastructure upgrade; key service roads between Wakad and Navale Bridge among priority projects
Pune Municipal Corporation Prioritizes 33 Missing Link Roads to Reduce Traffic Congestion
Pune Municipal Corporation Prioritizes 33 Missing Link Roads to Reduce Traffic CongestionThe Bridge Chronicle
Published on

Pune, 11 May 2026: The Pune Municipal Corporation (PMC) has decided to prioritize the construction of 33 missing link roads across the city as part of a major plan to reduce traffic congestion.

The civic body expects to spend nearly ₹1,200 crore on these projects, which include key service roads along both sides of the highway stretch between Wakad and Navale Bridge.

The PMC has started work on developing nearly 450 kilometres of missing link roads in Pune and newly merged areas following directions from Municipal Commissioner Naval Kishore Ram. The aim is to improve road connectivity and ease traffic movement in rapidly developing parts of the city.

Pune Municipal Corporation Prioritizes 33 Missing Link Roads to Reduce Traffic Congestion
Pune Traffic: Truck Breakdown on Mundhwa Bridge Causes Heavy Traffic Jam; Police Issued Diversion

Out of the 33 priority roads, land acquisition for 11 projects has reached the final stage, while work has already begun at one or two locations. PMC has also set a target of completing 10 missing link road projects this year.

One of the major projects is the construction of service roads on both sides of the highway between Wakad and Navale Bridge. PMC officials said nearly 50 per cent of the required land has already been acquired, while the process for acquiring the remaining land is expected to continue till December 2026. Another important road project in Dhayari is currently undergoing compulsory land acquisition.

Pune Municipal Corporation Prioritizes 33 Missing Link Roads to Reduce Traffic Congestion
Pune Shivajinagar Sizzles at 41.4°C, Highest May Temperature Since 2016

Ongoing Missing Link Road Works

  • Eklavya College to Kothrud Road

  • Baner Pancard Club to Murkute Vasti Road

  • Sutarwadi Bus Depot Road

  • New Airport Road to Viman Nagar Road

  • New Airport to Viman Nagar Road via Symbiosis

  • Chaudhary Vasti Fountain Road

  • Kirloskar Bridge to Magarpatta South Road

  • National Highway to Sun City Road

  • Funtime Sinhagad Road to Karvenagar Road

  • Navale Bridge to Bhoomkar Chowk Service Road

  • Sitaram Abaji Bibwe Road to Gururaj Society Road

PMC also expects several important road projects to be completed by December 2026 as part of the missing link program.

Road Projects Expected to be Completed by December 2026:

  • Rajaram Bridge to Dr Babasaheb Ambedkar Road Chowk

  • Dr Babasaheb Ambedkar Road to Rosary School Highway Stretch

  • Baner-Pashan Link Road

  • Ganaraj Chowk to Kaspate Vasti Road

  • Nagras Road, Aundh to Balewadi Stadium Road

  • Gunjan Chowk to Kalyani Nagar Road

  • VIT College to Kondhwa Road

  • Hume Pipe-Prayeja City Road to Dhayari via Kodre Farm

  • ABC Chowk to Tadigutta-NM Road

  • Mundhwa ROB to Keshavnagar Road

Pune Municipal Corporation Prioritizes 33 Missing Link Roads to Reduce Traffic Congestion
Silent March in Pune Demands Justice for Nasrapur Minor Assault Victim

“PMC has set a target of completing 21 out of the 33 missing link roads this year, while all 33 projects are expected to be completed within the next two years. Once these projects are finished, nearly 25 per cent of Pune’s traffic congestion problem could be reduced,” said Nikhil Mijar, Traffic Planner, PMC.

Join our WhatsApp Channel to Stay Updated!

Help Us Create the Content You Love

Take Survey Now!

Enjoyed reading The Bridge Chronicle?
Your support motivates us to do better. Follow us on Facebook, Instagram, Twitter and Whatsapp to stay updated with the latest stories.
You can also read on the go with our Android and iOS mobile app.

logo
The Bridge Chronicle
www.thebridgechronicle.com