Pune: Hadapsar–Yavat Elevated Corridor Work Gains Pace; Utility Shifting to Begin Soon, Pillar Construction From January 2027

Soil testing is underway at multiple locations along the 31.65-km corridor, while utility relocation will begin within a month to pave the way for uninterrupted construction.
Pune: Hadapsar–Yavat Elevated Corridor Work Gains Pace; Utility Shifting to Begin Soon, Pillar Construction From January 2027
Pune: Hadapsar–Yavat Elevated Corridor Work Gains Pace; Utility Shifting to Begin Soon, Pillar Construction From January 2027 (AI Generated)The Bridge Chronicle
Published on

Pune, 20th July 2026: Preparatory work for the much-awaited Hadapsar–Yavat Elevated Corridor has officially gained momentum, with the Maharashtra State Infrastructure Development Corporation (MSIDC) beginning soil testing at more than 10 locations along the proposed route.

While the main construction work has not yet started, officials have accelerated preliminary activities to ensure the project remains on schedule.

Join our WhatsApp Channel to Stay Updated!

The 31.65-km elevated corridor, estimated to cost ₹5,265 crore, is expected to significantly reduce traffic congestion on the busy Pune–Solapur Highway between Hadapsar and Yavat. Chief Minister Devendra Fadnavis recently performed the groundbreaking ceremony for the project and directed MSIDC to complete the corridor within three to three-and-a-half years, instead of the initially planned four-year timeline.

Pune: Hadapsar–Yavat Elevated Corridor Work Gains Pace; Utility Shifting to Begin Soon, Pillar Construction From January 2027
Pune: ₹30.83 Crore Approved for Alternative Road to Lohegaon Airport as Defence Access Closes

Following the completion of soil investigations, MSIDC will begin utility shifting within the next month. Water pipelines, high-voltage electricity lines, sewer networks, internet cables and telephone lines located along the corridor will be relocated before major civil works begin.

Officials said completing this work in advance will help avoid disruptions to essential services and ensure that pillar construction proceeds without delays.

Pune: Hadapsar–Yavat Elevated Corridor Work Gains Pace; Utility Shifting to Begin Soon, Pillar Construction From January 2027
Pune Civic Body Approves ₹73.52 Crore Shivajinagar Flyover to Ease Traffic Bottlenecks

According to the current project schedule, construction of the elevated corridor's pillars is expected to commence in January 2027. The advance planning is aimed at removing all obstacles before large-scale construction begins, helping the project progress smoothly.

The elevated corridor is expected to provide a long-term solution to chronic traffic congestion on the Hadapsar–Yavat stretch, one of the busiest sections of the Pune–Solapur Highway. Once completed, the project is expected to improve travel time, ease freight movement and enhance connectivity between Pune and the rapidly developing eastern suburbs.

Pune: Hadapsar–Yavat Elevated Corridor Work Gains Pace; Utility Shifting to Begin Soon, Pillar Construction From January 2027
Pune to Get 36.5-km Elevated Corridor as Metro Expansion and Solapur Road Flyovers Move Ahead

MSIDC Managing Director Brijesh Dixit said soil testing is progressing rapidly and utility shifting will begin shortly. He added that the agency is prioritising the removal of all obstacles before pillar construction so that the project can move ahead without interruptions while ensuring that water, electricity and communication services remain unaffected during execution.

Join our WhatsApp Channel to Stay Updated!

Help Us Create the Content You Love

Take Survey Now!

Enjoyed reading The Bridge Chronicle?
Your support motivates us to do better. Follow us on Facebook, Instagram, Twitter and Whatsapp to stay updated with the latest stories.
You can also read on the go with our Android and iOS mobile app.

logo
The Bridge Chronicle
www.thebridgechronicle.com